ELECTRICAL
SECTION 26 08 00
COMMISSIONING OF ELECTRICAL
PART 1 ‑ GENERAL
SCOPE
This section includes commissioning forms for construction verification and functional performance testing. Included are the following topics:
PART 1 - GENERAL
Scope
Related Work
Reference
Submittals
PART 2 - PRODUCTS
(Not Used)
PART 3 – EXECUTION
Commissioning Forms
CV-26 05 13 Medium-Voltage Cables
CV-26 05 19 Low-Voltage Electrical Power Conductors and Cables
CV-26 05 26 Grounding and Bonding for Electrical Systems
CV-26 05 33 Raceways and Boxes for Electrical Systems
CV-26 05 36 Cable Trays for Electrical Systems
CV-26 05 43 Underground Ducts and Raceways for Electrical Systems
CV-26 09 19 Enclosed Contactors
CV-26 09 28 Lighting Control Panels
CV-26 24 13 Switchboards
CV-26 24 16 Panelboards
CV-26 27 28 Disconnect Switches
CV-26 28 16 Enclosed Switches and Circuit Breakers
CV-26 29 00 Magnetic Motor Starters
CV-26 29 00 Manual Motor Starters
CV-26 29 00 Motor Control Centers
CV-26 43 13 Surge Protective Devices for Low-Voltage Electrical Power Circuits
CV-26 51 13 Interior Lighting Fixtures, Lamps and Ballasts
FPT-26 09 28 Lighting Control Panels
SUBMITTALS
Reference the General Conditions of the Contract for submittal requirements.
Reference Section 01 91 01 or 01 91 02 Commissioning Process for Construction Verification Checklist and Functional Performance Test submittal requirements.
PART 2 – PRODUCTS
(Not Used)
COMMISSIONING FORMS
Commissioning forms are to be filled in as work progresses by the individuals responsible for installation and shall be completed for each installation phase.
Provide a description of the work completed since the last entry, the percentage of the total work completed for the system for that area and the step of installation or finalization.
Circle Yes or No for each commissioning form item. If the information requested for an item does not apply to the given stage of installation for the system, list it as “N/A”. Explain all discrepancies, negative responses or N/A responses in the negative responses section.
Once the work is 100% complete and the responses to each item are complete and resolved for a given commissioning forms group, mark as complete, initial and date in the spaces provided.
Provide copies of the commissioning forms to the commissioning agent 2 days prior to construction progress meetings.
CV-26 05 13 – Medium-Voltage Cables
Equipment Identification/Tag: _______
Location: _________________________
A) CABLE PULLING CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
| YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| |||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) All water is pumped out of the manholes prior to beginning work.
2) A mandrel/swab ¼” smaller than the duct diameter is pulled through conduit run to insure adequate opening of conduit run.
3) Conduits swabbed to remove foreign material prior to pulling cables.
4) No cables pulled from an exterior location when the outdoor air temperature was below 40 deg. F.
5) Cable pulling done in accordance with cable manufacturer's recommendations, except as modified herein, and ANSI/IEEE C2 standards.
6) All cables pulled though conduit at the same time, with pulling lubricant used to ease pulling tensions.
7) Actual pulling tensions continuously monitored and permanently recorded in a log and submitted to the Engineer at the end of the project.
8) Excess cable provided at each termination and splice point for purpose of multiple terminations or splices to be performed.
9) Cables not to be terminated within 8 hours to be properly sealed and protected from moisture intrusion until termination.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) CABLE TERMINATIONS & SPLICES CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Splicing held to a minimum and only per pre-approved locations by Engineer.
2) Termination or splicing of the conductors are made with tool applied compression (swaged) fittings and conform to specification requirements for given cable type.
3) Installed lugs match the pads on the equipment to which the cable will be mounted.
4) All lug terminations are connected per connection torque valve as recommended by the manufacturer.
5) Spacers are used when more than one cable exists on an equipment pad.
6) Cable terminations are taped with approved anti-tracking tape.
7) Fireproofing applied to exposed cabling in manholes, vaults, and cable trays and cabling in pull boxes, troughs, switchgear pull sections, bases, and pulling pits containing two or more sets of cable.
8) Fireproofing material and installation meets specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) TESTING & FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) All exposed cabling has been visually inspected for physical damage and any damaged cabling has been replaced.
2) Cabling jacket and insulation are in good condition.
3) All cable terminations have been checked for proper tightness and clearances per specification and manufacturer recommendations and any adjustments necessary have been made.
4) All specified acceptance tests have been performed on all cables, terminations, and splices and are approved prior to energizing.
5) All splices and terminations are tagged in accordance with specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 05 19 – Low-Voltage Electrical Power Conductor and Cables
Equipment Identification/Tag: _______
Location: _________________________
A) CONDUCTOR AND CABLING PULLING CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Conductor and cabling sized to maintain less than a 3% voltage drop for rated length and ampacity of circuit.
2) Conductors and cabling coloring match specification requirements for given voltage, wire gauge, and leg of circuit.
3) Conduits swabbed to remove foreign material prior to pulling cables.
4) All cables pulled though conduit at the same time, with pulling lubricant used to ease pulling tensions.
5) Excess cable provided at each termination and splice point for purpose of multiple terminations or splices to be performed.
6) Emergency power conductors and cabling pulled in separate conduits from normal power systems.
7) Outdoor cables not to be terminated within 8 hours to be properly sealed and protected from moisture intrusion until termination.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) CONDUCTOR AND CABLE TERMINATIONS & SPLICES CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Installed lugs match the pads on the equipment to which the cable will be mounted.
2) All lug terminations are connected per connection torque valve as recommended by the manufacturer.
3) Splices made only in accessible junction boxes.
4) All conductors and cables cleaned prior to termination.
5) All splices made so that the electrical resistance of the splice does not exceed the equivalent resistance of 2’ of conductor.
6) Solderless spring type pressure connectors with insulating covers used for all wires splices and taps of conductors and cabling 10AWG and smaller.
7) Mechanical or compression connectors used for all wire splices and taps of conductors and cabling 8 AWG and larger.
8) Uninsulated conductors and connectors taped with electrical tape equivalent to 150% of the insulation value of the conductor.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) TESTING & FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) All exposed conductors and cabling has been visually inspected for physical damage and any damaged conductors and cabling has been replaced.
2) Conductors and cabling jacket and insulation are in good condition.
3) All cable terminations have been checked for proper tightness and clearances per specification and manufacturer recommendations and any adjustments necessary have been made.
4) For aluminum conductors and cabling all specified acceptance tests have been performed on all cables, terminations, and splices and are approved prior to energizing.
5) All splices and terminations are to be tagged within 2” to 4” of splice or termination and in accordance with specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 05 26 – Grounding and Bonding for Electrical Systems
Equipment Identification/Tag: _______
Location: _________________________
A) GENERAL GROUNDING AND BONDING INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Mechanical connections accessible for inspection and checking, with no insulation of connections.
2) Ground connection surfaces cleaned and all connections made permanent.
3) Grounds attached permanently before permanent building service is energized.
4) Grounding electrode conductors installed in PVC conduit or rigid galvanized steel conduit and bonded at both ends to the grounding electrode conductor with an approved grounding fitting.
5) Grounding electrode is correct size and length.
6) Grounded conductor run to each service disconnecting means and its enclosure.
7) Separate insulated equipment grounding conductor installed with phase conductors within each raceway.
8) All metallic systems (water, gas, sprinkler, etc.) and lightning protection system bonded to ground system.
9) System bonded within 5’ from point of entry into building to at least two of the following: metal underground water pipe, metal frame of building, concrete encased electrodes, ground ring, (underground local systems such as storage tanks, conduit, or piping), ground rod installed 8’ deep or at 45-degree angle and distanced a minimum of 6’ apart., ground plate buried 2-1/2’ deep.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) MEDIUM VOLTAGE GROUNDING AND BONDING INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Ground bus installed 18" above finished floor with insulated standoffs 36” on center, completely around the perimeter of the room (vault) containing the high voltage switchgear and unit substation.
2) Six ground rods provided equally spaced around high voltage switchgear room and connected to ground bus with 4/0 copper.
3) Separate 4/0 copper conductors provided from ground bus to, XO terminal of each transformer, each high voltage switch ground bus, and secondary service equipment ground bus.
4) Full size 600V copper THHN/THWN or XHHW-2 grounding conductor provided in each conduit, raceway or enclosure which contains high voltage conductors, and terminated at ground bus of equipment containing high voltage terminations.
5) Each enclosure containing high voltage parts (switches, fuses, transformers, pull boxes, etc.) bonded to room ground bus with 4/0 copper conductor.
6) All conduits containing high voltage conductors or secondary service conductors bonded to penetrated enclosures using grounding bushing and #4 copper conductor.
7) #10 stranded wire provided from each termination shield drain wire to ground bus within enclosure.
8) Ground rod provided in each section of each secondary switchboard with 4/0 copper wire connection to ground rod and to switchgear ground bus.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) LOW VOLTAGE (<600V) GROUNDING AND BONDING INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Code sized copper grounding electrode conductor provided from secondary switchboard ground bus, each separately derived system neutral, secondary service system neutral to street side of water meter, building steel, ground rod, and any concrete encased electrodes.
2) Bonding jumper provided around water meter.
3) Bond together system neutrals, service equipment enclosures, exposed non-current carrying metal parts of electrical equipment, metal raceway systems, grounding conductor bonded in raceways and cables, receptacle ground connectors, and plumbing systems.
4) Separate insulated equipment grounding conductor provided within each raceway.
5) Ground wire provided from each device to the respective enclosure.
6) Communications system grounding conductor provided at point of service entrance and connected to building common grounding electrode system.
7) Telecommunications and audio visual systems installed with an isolated grounding system with only one ground point at the electrical service entrance for the building per specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 05 33 – Raceway and Boxes for Electrical Systems
Equipment Identification/Tag: _______
Location: _________________________
A) CONDUIT & FITTINGS PRE-INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
YES NO | YES NO |
|
|
|
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Conduit type and material in accordance with specification requirements for given application and location.
2) Conduit sufficiently sized to accommodate cabling and fill requirements of contract document.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) CONDUIT & FITTINGS INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) | 10) | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Conduit support spacing complies with specification requirements.
2) All conduit supported independently of piping, ductwork, equipment, cable tray or other conduit.
3) Bends in conduit minimized with required bends conforming to specification requirements and no more than an equivalent of three 90 degree bends between boxes.
4) Moisture traps are avoided as much as possible. When unavoidable, a junction box is provided with drain fitting at conduit low point.
5) All equipment requiring maintenance is accessible.
6) Minimum 6” clearance between conduit and piping, and 12” clearance between conduit and heat sources such as flues, steam pipes, and heating appliances is provided.
7) No continuous conduit run exceeds 100’ without a junction box.
8) Expansion‑deflection joints installed where conduit crosses building expansion joints.
9) Where conduit passes between areas of differing temperatures, listed conduit seals are provided.
10) At end of work day suitable conduit caps or other approved seals provided for incomplete work to protect installed conduit against entrance of dirt and moisture.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) RACEWAY & GUTTER INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Raceway and gutter support spacing and methods comply with specification requirements.
2) All raceways supported independently of piping, ductwork, equipment, cable tray or other conduit.
3) Suitable insulating bushings and inserts provided at connections to outlets and corner fittings.
4) All equipment requiring maintenance is accessible.
5) Expansion‑deflection joints installed where conduit crosses building expansion joints.
6) Oil tight gutters included gaskets at each joint.
7) Rain-tight gutters are installed in horizontal position only.
8) At end of work day suitable caps or other approved seals provided for incomplete work to protect installed raceways and gutters against entrance of dirt and moisture.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
D) JUNCTION, PULL AND OUTLET BOXES INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Boxes provided in locations as per contract documents, Engineer’s direction or as necessary for splicing and terminations.
2) Box type and material in accordance with specification requirements for given application and location.
3) No outlet box located where it will be obstructed by other equipment, piping, lockers, benches, counters, etc.
4) All boxes supported independently of conduit, piping, ductwork, equipment, or cable tray.
5) No outlet boxes installed back‑to‑back in walls, and minimum 6” separation between all boxes, except for installations in acoustic walls where a minimum 24” separation between boxes is provided.
6) All boxes are accessible, and where installation is inaccessible, 18” by 24” access door has been provided.
7) Mounting heights for outlet boxes corresponds with contract document requirements.
8) All recessed outlet boxes in finished areas are mounted to the correct depth to accommodate and be flush to final surface finish.
9) Knockout closures provided for unused openings.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
E) FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) | 10) | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) All penetrations through fire rated wall assemblies have been sealed per specification requirements.
2) All penetrations through non-rated wall assemblies have been sealed per specification requirements for given space type.
3) Conduits that penetrate the building envelope are sealed to prevent intrusion of air and moisture and are accessible.
4) All conduit junction boxes are painted and tagged in accordance with specification requirements.
5) All splices and terminations are to be tagged within 2” to 4” of splice or termination and in accordance with specification requirements.
6) 1/8” nylon pull string provided in all empty conduits, except sleeves and nipples.
7) Grounding and bonding of conduits and raceways conform to specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 05 36 – Cable Trays for Electrical Systems
Equipment Identification/Tag: _______
Location: _________________________
A) CABLE TRAY INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) No sharp edges remain after field fabrication, and the metal cable tray is installed according to NEMA VE2 and manufacturer instructions.
2) The clearance between cable tray and other systems and equipment is a minimum of 1’ on both sides of the cable tray and 8”on top of the cable tray.
3) Tray does not restrict removal of ceiling panels or lighting assemblies. Cable tray location does not impede operation and access to other systems and equipment.
4) Supports provided at each connection point, at the end of each run, and at other points to maintain spacing between supports of 8’ maximum.
5) The maximum allowable deviation of the tray, from the level horizontal plane measured across the width of the tray, is one half of one inch (1/2"), with the tray loaded to capacity, as allowed by the NEC.
6) Expansion fittings are provided at expansion joints and where required.
7) Cable tray is grounded and bonded according to specifications or per NEC 250.96(A).
8) No conduits are attached to the cable tray except for the conduits that terminate at the cable tray.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Where cable tray passes below coils, traps, etc., covers are provided extending 12” on either side of cable tray.
2) Cable tray warning signs are installed at 15-foot intervals, e.g. WARNING! DO NOT USE CABLE TRAY AS WALKWAY, LADDER, OR SUPPORT FOR LADDERS OR PERSONNEL.
3) All penetrations through fire rated wall assemblies have been sealed per specification requirements.
4) All penetrations through non-rated wall assemblies have been sealed per specification requirements for given space type.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 05 43 – Underground Ducts and Raceways for Electrical Systems
Equipment Identification/Tag: _______
Location: _________________________
A) EXCAVATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Trench depth, width and height meet contract document requirements.
2) Bottom of trench consists of undisturbed earth or filled to proper level with mechanically compacted sand for low grade trenches.
3) Entire trench section excavated and graded before any duct is laid in section.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) CONDUIT IINSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) | 10) | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Heavy wall galvanized steel conduit provided within 5’ of each building wall or manhole wall penetration, within the concrete envelope to provide protection against vertical shearing.
2) Mechanical seal of assembled rubber links properly sized for conduit is provided for all penetrations into existing facilities.
3) Flush bell ends provided on duct at manholes and buildings.
4) Spacers provided as recommended by conduit manufacturer and specification requirements.
5) Conduit joints staggered a minimum of 6” horizontally for concrete encasement applications.
6) Conduit pitched for proper drainage to manhole or pull box a minimum of 4” per 100’.
7) Not more than one 90 degree bend or equivalent between pull points for primary conduit and two 90 degree bends or equivalent for signal conduit is provided.
8) Insulated grounding bushings provided on steel duct ends.
9) At end of work day suitable caps or other approved seals provided for incomplete work to protect installed conduits against entrance of dirt and moisture.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) CONDUIT FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO |
|
|
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) A mandrel/swab ¼” smaller than the duct diameter is pulled through conduit run to insure adequate opening of conduit run.
2) Pull tape with measurement markings provided in each empty duct.
3) All steel bushings grounded per specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
D) BACKFILL & CONCRETE PLACEMENT CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Reinforcing bars installed at a minimum at each corner, with a 12” overlap of the joints and tied the connecting walls of manholes, vaults, and buildings, etc.
2) Minimum of 3” of concrete cover over conduit at the top, bottom and sides of the duct bank is provided with a troweled crowned top on the concrete to prevent water accumulation.
3) Concrete envelope extended to finish floor grade or interior wall surface in buildings and finish pad grade at equipment.
4) Top of concrete envelopes is more than 24” below grade.
5) Underground warning tape provided 12" below finish grade over all ductbanks.
6) All backfill is compacted around ductbank and all ground and pavement surfaces returned to intended or original condition.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
CV-26 09 19 – Enclosed Contactors
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Ampere Ratings (A) |
|
| ||
6 | Short Circuit Current Rating (kA) |
|
| ||
7 | # of Poles |
|
| ||
8 | Enclosure Type |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Unit is level, plumb, and square. | YES | NO | ||
4 | Identification labels provided per specification requirements. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is grounded per project requirements. | YES | NO | ||
2 | All connections are terminated properly. | YES | NO | ||
3 | All electrical connections are tightened to the proper torque values. | YES | NO | ||
4 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | CONTROLS INSTALLATION | ||||
1 | Remote start and stop wiring installed and communication verified. | YES | NO | ||
2 | Photocell wiring installed and communication verified (if applicable). | YES | NO | ||
3 | Time-clock wiring installed and communication verified (if applicable). | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | STARTUP | ||||
1 | All protective coverings removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | All wiring connections verified for proper torques values and are acceptable. | YES | NO | ||
4 | Voltage verified to be zero across line and load terminals of each relay. | YES | NO | ||
5 | Unit energized by authorized personnel. | YES | NO | ||
6 | All relays tested via H-O-A switch and are operational. | YES | NO | ||
7 | All damage to unit finish is repaired. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
G | CONTROLS STARTUP | ||||
1 | Unit programmed in accordance with contract documents and manufacturer instructions. | YES | NO | ||
2 | Communication with building automation system verified (if applicable). | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 09 28 – Lighting Control Panels
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Amperage Rating (A) |
|
| ||
6 | KAIC rating (kA) |
|
| ||
7 | Max / Installed Relays | / | / | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Unit is level, plumb, and square. | YES | NO | ||
4 | Identification labels provided per specification requirements. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is grounded per project requirements. | YES | NO | ||
2 | All connections are terminated properly. | YES | NO | ||
3 | All electrical connections are tightened to the proper torque values. | YES | NO | ||
4 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | CONTROLS INSTALLATION | ||||
1 | Remote low-voltage switch wiring installed and communication verified. | YES | NO | ||
2 | Photocell wiring installed and communication verified (if applicable). | YES | NO | ||
3 | Time-clock wiring installed and communication verified (if applicable). | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | STARTUP | ||||
1 | All protective coverings removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | All wiring connections verified for proper torques values and are acceptable. | YES | NO | ||
4 | Voltage verified to be zero across line and load terminals of each relay. | YES | NO | ||
5 | Unit energized by authorized personnel. | YES | NO | ||
6 | All relays tested via override switch and are operational. | YES | NO | ||
7 | All damage to unit finish is repaired. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
G | CONTROLS STARTUP | ||||
1 | Unit programmed in accordance with contract documents and manufacturer instructions. | YES | NO | ||
2 | Communication with building automation system verified (if applicable). | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 24 13 – Switchboards
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | # of Wires |
|
| ||
6 | Main Amps (A) |
|
| ||
7 | Circuit Count |
|
| ||
8 | kAIC Rating (kA) |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
3 | Power conduit openings are plugged. | YES | NO | ||
4 | Unit tags affixed. | YES | NO | ||
5 | Manufacturer’s ratings readable/accurate. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Concrete housekeeping pad provided for unit at location specified in contract documents. | YES | NO | ||
2 | Power conduit “stub-ups” are “roughed-in” to the slab at the proper locations and conduits plugged close. | YES | NO | ||
3 | Conduit feeds are aligned with openings and accommodate seismic motion. | YES | NO | ||
4 | Unit secured as required by manufacturer, specifications, and seismic zone requirements. | YES | NO | ||
5 | Adequate clearance around unit for service and applicable codes. | YES | NO | ||
6 | Adequate clearance between the ceiling and top of switchgear. | YES | NO | ||
7 | Unit sections connected per manufacturer instructions. | YES | NO | ||
8 | Through-bus and ground-bus splice connections/kits between unit sections have been installed. | YES | NO | ||
9 | Unit is level and all sections plumb and square per manufacturer’s layout diagram. | YES | NO | ||
10 | Unit identification attached and visible. | YES | NO | ||
11 | Temporary filters provided for ventilation opening prior to energizing. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Ground bus has been installed. | YES | NO | ||
2 | Internal cabling supported independently of terminations. | YES | NO | ||
3 | Unit is adequately grounded and bonded for intended use. | YES | NO | ||
4 | Proper phasing has occurred in relationship to phase conductors. | YES | NO | ||
5 | All connections are terminated properly. | YES | NO | ||
6 | All electrical connections are tight. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | Temporary filters and protective coverings removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | Insulators and supports show no signs of damage or cracks. | YES | NO | ||
4 | Current transformers secured and wired per manufacturer instructions (metering applications ONLY). | YES | NO | ||
5 | All switches and circuit breakers have been manually tested. | YES | NO | ||
6 | All electronic circuit breaker settings have been adjusted to desired setting (if applicable). | YES | NO | ||
7 | Fuses have been installed in all switches (if applicable). | YES | NO | ||
8 | Ground-fault-protection (GFP) trip and time delays have been adjusted to desired setting (if applicable). | YES | NO | ||
9 | All wiring connections verified for proper torques values and are acceptable. | YES | NO | ||
10 | Phase-to-phase, phase-to-ground, and neutral-to-ground, and dielectric tests have been accomplished and results are acceptable. | YES | NO | ||
11 | No hazards or adverse circumstances exist per continuity and high potential tests. | YES | NO | ||
12 | Insulation megger test at 1000V accomplished and results acceptable. | YES | NO | ||
13 | Unit energized by authorized personnel. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | TESTING & FINALIZATION | ||||
1 | Solid state circuit breaker self-diagnostics completed. | YES | NO | ||
2 | Electronic circuit breaker trip unit tests completed and results acceptable (if applicable). | YES | NO | ||
3 | Ground-fault-protection (GFP) system tested and certified (if applicable). | YES | NO | ||
4 | Proper warning and labeling signage provided. | YES | NO | ||
5 | All damage to unit finish is repaired. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 24 16 – Panelboards
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Catalog Number |
|
| ||
4 | Voltage / Phase / Frequency (V / - /Hz) | / / | / / | ||
5 | Main Amps (A) |
|
| ||
6 | Circuit Count |
|
| ||
7 | kAIC rating (kA) |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
3 | Circuit breaker capacities documented. | YES | NO | ||
4 | Unit tags affixed. | YES | NO | ||
5 | Manufacturer’s ratings readable/accurate. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacture, specifications, and seismic zone requirements. | YES | NO | ||
2 | Adequate clearance around unit for service per table NEC-110.26. | YES | NO | ||
3 | Top of tub set at 6’ from finished floor unless specified otherwise in contract documents. | YES | NO | ||
4 | Conduit feeds are aligned with openings and accommodate seismic motion. | YES | NO | ||
5 | Unit is level, plumb, and square. | YES | NO | ||
6 | Unit labeled and is easy to see. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Three spare ¾” empty conduits provided (recessed units ONLY). | YES | NO | ||
2 | Unit is adequately grounded to grounding lug for intended use. | YES | NO | ||
3 | Proper phasing has occurred in relationship to phase conductors. | YES | NO | ||
4 | All connections are terminated properly. | YES | NO | ||
5 | All electrical connections are tight. | YES | NO | ||
6 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | All protective coverings have been removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | Insulators and supports show no signs of damage or cracks. | YES | NO | ||
4 | Current transformers secured and wired per manufacturer instructions (metering applications ONLY). | YES | NO | ||
5 | All electronic circuit breaker settings have been adjusted to desired setting (if applicable). | YES | NO | ||
6 | Ground-fault-protection (GFP) trip and time delays have been adjusted to desired setting (if applicable). | YES | NO | ||
7 | All wiring connections verified for proper torques values and are acceptable. | YES | NO | ||
8 | Phase-to-phase, phase-to-ground, and neutral-to-ground, and dielectric tests have been accomplished and results are acceptable. | YES | NO | ||
9 | No hazards or adverse circumstances exist per continuity and high potential tests. | YES | NO | ||
10 | Insulation megger test accomplished and results acceptable. | YES | NO | ||
11 | Unit energized by authorized personnel. | YES | NO | ||
12 | All damage to unit finish is repaired. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | TESTING & FINALIZATION | ||||
1 | Overcurrent protective devices have been manually exercised. | YES | NO | ||
2 | Solid state circuit breaker self-diagnostics completed. | YES | NO | ||
3 | Electronic circuit breaker trip unit tests completed. | YES | NO | ||
4 | Ground-fault-protection (GFP) system tested and certified. | YES | NO | ||
5 | Filler plates provided for all unused spaces. | YES | NO | ||
6 | As-built circuit index provided and attached to interior of unit door. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 27 28 – Disconnect Switches
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Ampere Rating (A) |
|
| ||
6 | kAIC Rating (kA) |
|
| ||
7 | Horsepower Rating (HP) |
|
| ||
8 | Enclosure Type |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
3 | Unit tags affixed. | YES | NO | ||
4 | Manufacturer’s ratings readable/accurate. | YES | NO | ||
5 | Unit is rated “Heavy Duty”. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Conduit feeds are aligned with openings and accommodate seismic motion. | YES | NO | ||
4 | Unit is level, plumb, and square. | YES | NO | ||
5 | Unit labeled and is easy to see. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is adequately grounded for intended use. | YES | NO | ||
2 | All connections are terminated properly. | YES | NO | ||
3 | All electrical connections are tight. | YES | NO | ||
4 | All cables are permanently labeled relative to use. | YES | NO | ||
5 | Fuses have been installed in all switches. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 28 16 – Enclosed Switches and Circuit Breakers
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Ampere Rating (A) |
|
| ||
6 | kAIC Rating (kA) |
|
| ||
7 | Enclosure Type |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
3 | Unit tags affixed. | YES | NO | ||
4 | Manufacturer’s ratings readable/accurate. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Conduit feeds are aligned with openings and accommodate seismic motion. | YES | NO | ||
4 | Unit is level, plumb, and square. | YES | NO | ||
5 | Unit labeled and is easy to see. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is adequately grounded for intended use. | YES | NO | ||
2 | All connections are terminated properly. | YES | NO | ||
3 | All electrical connections are tight. | YES | NO | ||
4 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | Electronic circuit breaker settings have been adjusted to desired setting (if applicable). | YES | NO | ||
2 | Overcurrent protective devices have been manually exercised. | YES | NO | ||
3 | Electronic circuit breaker trip unit test completed. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 29 00 – Magnetic Motor Starters
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Ampere Rating (A) |
|
| ||
6 | kAIC Rating (kA) |
|
| ||
7 | Horsepower Rating (Hp) |
|
| ||
8 | NEMA Size |
|
| ||
9 | Motor Being Served |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Unit is level, plumb, and square. | YES | NO | ||
4 | Identification labels provided per specification requirements. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is grounded per project requirements. | YES | NO | ||
2 | Heater elements installed and sized properly for motor being controlled. | YES | NO | ||
3 | All connections are terminated properly. | YES | NO | ||
4 | All electrical connections are tightened to proper torque values. | YES | NO | ||
5 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | Circuit breaker settings have been adjusted to desired setting (if applicable). | YES | NO | ||
2 | Fuses have been installed in all switches (if applicable). | YES | NO | ||
3 | Overcurrent protective devices have been manually exercised. | YES | NO | ||
4 | Operation of unit and associated motor verified and acceptable. | YES | NO | ||
5 | All indicating lamps are operational. | YES | NO | ||
6 | Communication with building automation system verified (if applicable). | YES | NO | ||
7 | Motor data sheet provided on interior door of unit. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 29 00 – Manual Motor Starters
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | Ampere Rating (A) |
|
| ||
6 | kAIC Rating (kA) |
|
| ||
7 | Horsepower Rating (Hp) |
|
| ||
8 | NEMA Size |
|
| ||
9 | Motor Being Served |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit secured as required by manufacturer and specification requirements. | YES | NO | ||
2 | Adequate clearance around unit for service. | YES | NO | ||
3 | Unit is level, plumb, and square. | YES | NO | ||
4 | Identification labels provided per specification requirements. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is grounded per project requirements. | YES | NO | ||
2 | Heater elements installed and sized properly for motor being controlled. | YES | NO | ||
3 | All connections are terminated properly. | YES | NO | ||
4 | All electrical connections are tightened to proper torque values. | YES | NO | ||
5 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | Operation of unit and associated motor verified and acceptable. | YES | NO | ||
2 | All indicating lamps are operational. | YES | NO | ||
3 | Motor data sheet provided on interior door of unit. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 29 00 –Motor Control Centers
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | # of Wires |
|
| ||
6 | Main Amps (A) |
|
| ||
7 | Circuit Count |
|
| ||
8 | kAIC Rating (kA) |
|
| ||
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Concrete housekeeping pad provided for unit at location specified in contract documents. | YES | NO | ||
2 | Power conduit “stub-ups” are aligned with openings. Conduits plugged closed. | YES | NO | ||
3 | Independent conduits provided for control wiring. | YES | NO | ||
4 | Unit secured as required by manufacturer, specifications, and seismic zone requirements. | YES | NO | ||
5 | Adequate clearance around unit for service and applicable codes. | YES | NO | ||
6 | Unit sections attached per manufacturer instructions (if applicable). | YES | NO | ||
7 | Through-bus and ground-bus splice connections/kits between unit sections have been installed. | YES | NO | ||
8 | Unit is level and all sections plumb and square per manufacturer’s layout diagram. | YES | NO | ||
9 | Identification labels provided per specification requirements. | YES | NO | ||
10 | Temporary filters provided for ventilation opening prior to energizing. | YES | NO | ||
11 | Insulators and supports show no signs of damage or cracks. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Ground bus has been installed. | YES | NO | ||
2 | Internal cabling supported independently of terminations. | YES | NO | ||
3 | Unit is grounded per project requirements. | YES | NO | ||
4 | Proper phasing has been verified between phase conductors and bus phases. | YES | NO | ||
5 | All connections are terminated properly. | YES | NO | ||
6 | All electrical connections are tightened to proper torque values. | YES | NO | ||
7 | All cables are permanently labeled relative to use. | YES | NO | ||
8 | Current transformers secured and wired per manufacturer instructions (if applicable). | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | Temporary filters and protective coverings removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | All switches and circuit breakers have been manually tested. | YES | NO | ||
4 | All electronic circuit breaker settings have been adjusted to desired setting (if applicable). | YES | NO | ||
5 | Each motor circuit protector has been adjusted to the full load amperes of the motor it serves (if applicable). | YES | NO | ||
6 | Fuses have been installed in all switches (if applicable). | YES | NO | ||
7 | Phase-to-phase, phase-to-ground, neutral-to-ground, and dielectric tests have been accomplished and results are acceptable. | YES | NO | ||
8 | No hazards or adverse circumstances exist per continuity and high potential tests. | YES | NO | ||
9 | Insulation megger test accomplished and results acceptable. | YES | NO | ||
10 | Unit energized by authorized personnel. | YES | NO | ||
11 | Indicating lamps function properly. | YES | NO | ||
12 | Operation of unit and associated motor verified and acceptable. | YES | NO | ||
13 | Ensure indicating lights are the “Push-to-test” type with LED lamps and “Red” covers. | YES | NO | ||
14 | Ensure control transformer primary/secondary conductors are fused and have “X2” terminal grounded. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | TESTING & FINALIZATION | ||||
1 | Each starter within the MCC has been individually commissioned. | YES | NO | ||
2 | Communication with building automation system verified. | YES | NO | ||
3 | Motor data sheet provided on interior door of each starter. | YES | NO | ||
4 | Proper warning and labeling signage provided. | YES | NO | ||
5 | All damage to unit finish is repaired. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 43 13 – Surge Protective Devices for Low-Voltage
Electrical Power Circuits
Equipment Identification/Tag: _______
Location: _________________________
Group/Item | Group/Task Description | Submitted | Delivered | ||
A | MODEL VERIFICATION | ||||
1 | Manufacturer |
|
| ||
2 | Model |
|
| ||
3 | Serial Number |
|
| ||
4 | Voltage (V) |
|
| ||
5 | SCCR - Short Circuit Current Rating (kA) |
|
| ||
6 | VPR - Voltage Protective Rating L-L, L-G, N-G (V / V / V) | / / | / / | ||
7 | Associated Switchboard or Panelboard |
|
| ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
Group/Item | Group/Task Description | Response | |||
B | PHYSICAL CHECKS | ||||
1 | Unit is free from physical damage. | YES | NO | ||
2 | All components/accessories present. | YES | NO | ||
3 | Unit tags affixed. | YES | NO | ||
4 | Manufacturer’s ratings readable/accurate. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
C | INSTALLATION | ||||
1 | Unit location does not exceed manufacturer's recommended lead length between unit and load. | YES | NO | ||
2 | Unit secured as required by manufacture, specifications, and seismic zone requirements. | YES | NO | ||
3 | Adequate clearance around unit for service. | YES | NO | ||
4 | Unit labeled and is easy to see. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
D | WIRING | ||||
1 | Unit is adequately grounded and bonded for intended use. | YES | NO | ||
2 | Integral or external disconnect provided for SPD. | YES | NO | ||
3 | Proper phasing has occurred in relationship to phase conductors. | YES | NO | ||
4 | All connections are terminated properly. | YES | NO | ||
5 | All electrical connections are tight. | YES | NO | ||
6 | All cables are permanently labeled relative to use. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
E | STARTUP | ||||
1 | All protective coverings have been removed. | YES | NO | ||
2 | Unit has been cleaned of all debris and dirt on interior of unit. | YES | NO | ||
3 | All switches and circuit breakers have been manually tested. | YES | NO | ||
4 | All wiring connections verified for proper torques values and are acceptable. | YES | NO | ||
5 | Unit energized by authorized personnel. | YES | NO | ||
6 | Indicating LEDs function properly. | YES | NO | ||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | | |
F | TESTING & FINALIZATION | ||||
1 | Phase diagnostic test performed and results satisfactory. | YES | NO | ||
2 | Ground continuity test accomplished and results acceptable. | YES | NO | ||
3 | Surge counter operational. | YES | NO | ||
Negative Responses
Group/ Item | Date Found | Found By | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO | ||||||
YES / NO |
CV-26 51 13 – Interior Light Fixtures, Lamps and Ballasts
Equipment Identification/Tag: _______
Location: _________________________
A) INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) | 10) | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Fixtures, ballasts, and lamps are free from damage.
2) Identical ballasts provided for each fixture type.
3) All fixtures and exit signs installed in locations specified in contract documents.
4) Fixtures do not impede access to other systems or equipment for maintenance.
5) Suspended fixtures and exit signs are hung independent of any other fixture, system, or equipment, are level, and are suspended with appropriate materials and methods defined within the contract documents.
6) Fixtures larger than 2’x4’ or greater than 50 lbs. are supported independently from ceiling framing.
7) All recessed fixtures are installed flush to ceiling or wall finish.
8) All recessed fixtures are installed to permit removal and access to lamps from below.
9) All wall mounted fixtures and exit signs are mounted at heights specified in contract documents.
10) All fixtures are supported and installed in accordance with manufacturer and specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
B) WIRING INSTALLATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO | YES NO |
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Fixture and accessories grounded and bonded to branch circuit grounding conductor.
2) Maximum of 6’ of flexible conduit provided for lay-in, recessed fixtures.
3) All electrical connections are tight.
4) All conductors are labeled per specification requirements.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
C) STARTUP & TESTING CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
YES NO | YES NO | YES NO | YES NO |
|
|
|
|
|
| ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Emergency indicating button/lamp visible and verified to be operational (if applicable).
2) Associated emergency ballast tested and operation verified (if applicable).
3) Occupancy sensor and associated fixture(s) tested and operation verified (if applicable).
4) Lighting control schedules programmed and operation verified for all associated fixtures (if applicable).
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
D) FINALIZATION CHECKS
Date | Description of Work Performed | % Complete | Initials | Questions (See details below) | |||||||||
1) | 2) | 3) | 4) | 5) | 6) | 7) | 8) | 9) | 10) | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | YES NO | ||||
q CHECKLIST GROUP COMPLETE | INITIALS: | | DATE: | |
Question Details
1) Protective covering removed.
2) Lens, trim ring and other architectural accessories installed.
3) Recessed fixtures are flush to finished surface with no visible gaps.
4) Code-required hardware is installed to secure recessed grid-supported fixtures in place.
5) Recessed fixtures in fire rated assemblies have been sealed per manufacturer and specification requirements to maintain assembly rating.
6) Number and type of lamps specified for each fixture installed and operational.
7) Fluorescent lamps installed in fixtures with dimming ballasts have been burned in at 100% rated output for a minimum of 100 hours.
8) Fixture adjusted and aimed for specific task or effect per contract documents and/or Architect’s directions.
9) All damages to fixture finish repaired.
10) Fixtures and lens are clean.
Negative Responses
Group/Item | Date Found | Found By | Location | Reason for Negative Response | Resolved | Date Resolved | Resolution |
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO | |||||||
YES / NO |
FPT-26 09 28 – Lighting Control Panels
Equipment Identification/Tag: _______
Location: _________________________
Test Duration
Date: | Start Time: | End Time | |||
Estimated Duration: | |||||
Cx Provider(s): | |||||
Applicable Equipment: | |||||
Objectives
This test is performed to investigate the functionality of the low voltage lighting controls.
Instrumentation
Instrument | Accuracy | Measurement |
N/A | N/A | N/A |
Stated Sequence
To be defined by A/E and commissioning provider.
Sampling Set
All sequences for a minimum of 20% of the total areas present. However, ensure at least one area representing each lighting control method is tested.
Procedure
Results
Manual Control (if applicable):
Room # | Switch ID | Relay # | Fixture ID | # of Fixtures | Accepted? | Notes |
Y / N | ||||||
Y / N | ||||||
Y / N |
Schedule Control (if applicable):
Room # | Fixture ID | # of Fixtures | Accepted? | Notes |
Y / N | ||||
Y / N | ||||
Y / N |
Occupancy Control (if applicable):
Room # | Occupancy Sensor Time-out Setting | Fixture ID | # of Fixtures | Accepted? | Notes |
Y / N | |||||
Y / N | |||||
Y / N |
Daylighting Control (if applicable):
Room # | Design Light Levels (f-c) | Initial Light Levels (f-c) | Test Light Levels (f-c) | Fixture ID | # of Fixtures | Accepted? | Notes |
Y / N | |||||||
Y / N | |||||||
Y / N |
Conclusion
Acceptable Criteria: All schedules and lighting levels comply with contract documents. All lights turn on and off when called for by switch, schedule and/or sensor.
Comments:
Observations:
Final Status: q Accepted q Not Accepted
Relevant Trend Data
N/A
Witnesses
Name |
| Signature |
|
|
|
| ||
|
|
|
| ||
|
|
|
| ||
|
|
|
|
FPT-26 32 13.13 and 26 32 13.16 – Engine-Driven Generator Sets
Equipment Identification/Tag: _______
Location: _________________________
Test Duration
Date: | Start Time: | End Time | |||
Estimated Duration: | |||||
Cx Provider(s): | |||||
Applicable Equipment: | |||||
Objectives
This test is performed to investigate the functionality of the generator to provide emergency power to the facility in concert with automatic transfer switches upon loss of normal power.
Instrumentation
Instrument | Accuracy | Measurement |
N/A | N/A | N/A |
Sampling Set
All units and all sequences.
Procedure
i. Verify facility is being supplied by emergency power system only.
ii. Using the final as-built documentation and the Lighting table under the results section, systematically verify the fixtures noted to be supplied by emergency power are energized.
i. Verify facility is being supplied by emergency power system only.
ii. Using the final as-built documentation and the Receptacle Loads table under the results section, systematically verify the receptacles noted to be supplied by emergency power are powered via a receptacle test plug.
i. Verify facility is being supplied by emergency power system only.
ii. Using the BAS system and the Process/Equipment Loads table under the results section, systematically verify the connected equipment is operational by manually overriding each unit through the BAS system.
Results - Power Transfer
Generator starts in response to loss of utility power? | Y / N |
Time Delay Between Loss of Power and Generator Start-up: | |
ATS properly transfers power to generator without any issues or hitches in transfer? | Y / N |
Generator enunciator panel clearly indicates generator and emergency mode power operation? | Y / N |
ATS transfers power back to utility feed in response to restoration of utility feed? | Y / N |
Generator enunciator panel clearly indicates transfer of power back to utility feed? | Y / N |
Generator successfully shuts down after cool down period? | Y / N |
Time From Transfer to Utility Feed to Generator Shut Down: |
Emergency Load Tests
Lighting
Room # | Circuit # | Fixture ID | # of Fixtures | Accepted? | Notes |
Y / N | |||||
Y / N | |||||
Y / N |
Receptacle Loads
Room # | Circuit # | # of Recpt. | Accepted? | Notes |
Y / N | ||||
Y / N | ||||
Y / N |
Process/Equipment Loads
Unit Tag | Circuit # | Accepted? | Notes |
Y / N | |||
Y / N | |||
Y / N |
Conclusion
Acceptable Criterion: Generator and ATS transfer power without issue and in accordance with specified time delays for power transfer and cool down, all attached loads to emergency power comply with as-built documentation and are operational.
Comments:
Observations:
Final Status: q Accepted q Not Accepted
Relevant Trend Data
N/A
Witnesses
Name |
| Signature |
|
|
|
|
|
|
END OF SECTION
IDENTIFICATION FOR ELECTRICAL SYSTEMS
Radha Krishna Temple Construction